SmartGridCity is a Smart Grid Flop

The latest ugly data unearthed about the flagship smart grid project SmartGridCity in Boulder Colo. — one of the most widely publicized experiments in bringing smart grid systems to an entire city — is cringe-worthy. According to SmartGridNews, which dug through Colorado Public Utility Commission filings, the project was woefully mismanaged, and didn’t follow the proper procedures or do the proper cost benefit analysis before it was started.

By now most of you know that SmartGridCity, the showcase smart grid project from utility Xcel Energy, has gone way over budget. As we noted back in February the latest estimate for a project that was projected to cost $15.3 million, has risen to an estimated $42.1 million, and that doesn’t include operations and maintenance (the entire project is expected to cost in excess of $100 million). SmartGridNews says the project is now estimated to cost $44.8 million.

According to Xcel, it was the cost of building the fiber optic network that serves as the backbone of SmartGridCity’s communications, a task that was given to consortium partner Current Group, that’s one of the main culprits responsible for the ballooning cost. Not only did the utility need far more underground fiber than it originally anticipated, it also faced other unexpected costs, such as using diamond-tipped drill bits to tear through granite and bringing in cranes and dump trucks to remove boulders, the utility reported in a May 2009 document.

But the real problem is that Xcel, and the who’s who of industry partners in the group, which included GridPoint, Accenture, Current Group, SmartSynch, Ventyx and OSISoft, didn’t perform a cost-benefit analysis prior to starting the project, says SmartGridNews. In addition to no cost analysis, the group originally didn’t file for a “Certificate of Public Convenience and Necessity,” back in 2008 when the project started, which is a filing that would have enabled the PUC to cap costs of the project to protect rate payers. SmartGridNews says that Xcel didn’t file this because “they didn’t think they needed to for what they deemed a research project.” That’s an expensive bit of research.

The project was getting so pricey that in 2009, Xcel asked the PUC to approve a rate increase so that it could recoup some of its costs. In December 2009 the PUC approved an $11 million rate hike to cover additional costs (among other things) but told Xcel it now needed to go through the process of filing a CPCN and it needed to prove why it needed to increase rates. The rate increase and the details of the request for CPCN, are what has been leaking out all these ugly details and media coverage of the mismanagement in this smart grid saga.

SmartGridNews says now that the project is almost done, only 43 percent of Boulder residents have smart meters and the installed metering systems are not providing as many benefits as anticipated. Overall: smart grid FAIL.

For more research on the smart grid check out GigaOM Pro (subscription required):

Report: Open Source & the Smart Grid

Home Energy Management: Consumer Attitudes and Choices

Cisco Seizes Smart Grid Low Hanging Fruit

loading

Comments have been disabled for this post